The proposed 2026 MSGP could change how industrial facilities monitor stormwater, report problems, and plan for severe weather. EPA’s January 2025 webinar outlined proposed requirements for its Multi-Sector General Permit, including expanded monitoring and faster follow-up when results identify concerns.
For facility managers, the proposals offer a useful starting point for reviewing stormwater programs and preparing for a future permit transition.
What Is the 2026 MSGP?
The 2026 MSGP is EPA’s proposed replacement for the 2021 Multi-Sector General Permit for industrial stormwater discharges. It would apply to eligible facilities in areas where EPA is the permitting authority. Most industrial facilities obtain stormwater permit coverage through their state, so operators should confirm which program applies to their location. EPA’s industrial stormwater overview
Status update: EPA did not issue a replacement before the 2021 MSGP expired on February 28, 2026. EPA reports that the existing permit has been administratively continued for operators covered before expiration. The changes discussed below are proposals, rather than current requirements. EPA’s permit update
Proposed 2026 MSGP Monitoring Changes
EPA’s webinar proposed quarterly benchmark monitoring during the first three years of coverage, with conditions for discontinuing monitoring after sufficient samples and qualifying results.
The proposal also identified 11 subsectors for a shift from indicator monitoring to benchmark monitoring and Additional Implementation Measures (AIM). For discharges to impaired waters, EPA proposed quarterly monitoring throughout the permit term, whether or not the receiving water has an approved or established total maximum daily load. EPA’s webinar presentation
Facilities can prepare by reviewing their sector classification, sampling arrangements, and process for evaluating laboratory results.
Faster Inspections and Reporting
Under the proposed 2026 MSGP, an AIM triggering event would require a report describing planned corrective action within 14 days. A follow-up report would be due within 14 days of completing that action.
An AIM Level 1 event would also require a documented inspection within seven days to investigate the cause of a benchmark exceedance. EPA’s webinar presentation
These proposed deadlines make clear responsibilities essential. Facilities should establish who receives laboratory results, evaluates potential triggers, coordinates inspections, and submits reports.
PFAS Monitoring for Specified Sectors
EPA proposed quarterly, report-only monitoring for 40 PFAS compounds in specified industrial sectors, using EPA Method 1633.
This indicator monitoring would have no benchmark threshold and would not, by itself, trigger Part 5 follow-up actions. Applicable water quality requirements would still apply. EPA explains that the results would help characterize PFAS in industrial stormwater and inform consideration of future monitoring requirements. EPA’s proposed permit fact sheet
Potentially affected facilities can begin discussing sampling procedures, laboratory capacity, and anticipated costs with their analytical providers.

Stormwater Controls for Major Storms
The proposal would require operators to consider past exposure and future risks from major storms and flooding when selecting stormwater controls, using the best available data.
EPA’s fact sheet explains that operators would need to consider the benefits of resilient controls, while allowing them to determine that additional controls are unnecessary. EPA’s proposed permit fact sheet
Reviewing previous incidents of erosion, overtopping, or exposure of stored materials can help facilities identify weaknesses in their stormwater pollution prevention plans.
How to Prepare for the 2026 MSGP
A practical preparation plan starts with five steps:
- Confirm the permitting authority and industrial sector that apply to your facility.
- Review sampling procedures and laboratory arrangements.
- Assign responsibility for reviewing results and coordinating responses.
- Evaluate stormwater controls against past storm damage and potential flooding.
- Review your stormwater pollution prevention plan and follow EPA’s current transition guidance.
EPA’s webinar provides a useful overview of the proposed 2026 MSGP changes. Facilities should use it alongside current permit guidance to prepare for possible changes while meeting their existing obligations.